Question 17
1.00/0.00
You are a project manager and working with procurements for your projects. You are meeting seller to identify the performance of seller concerning SOW and also to see how work is getting performed. You are looking at quality audit documents created during execution of work by seller’s quality department. What are you trying to do in this scenario?
Manage change control system for project
Procurement performance review
Inspection and Audit
Performance reporting
As per answer - Option B Procurement Performance Review
but in PMBOK page 498 the procurement review does not include review of quality audit (it includes analyze quality?) .
As I understand the PM is carrying out Inspection and Audit.
If you can please confirm.
Thanks
This is from Izenbridge test
Question 17
1.00/0.00
You are a project manager and working with procurements for your projects. You are meeting seller to identify the performance of seller concerning SOW and also to see how work is getting performed. You are looking at quality audit documents created during execution of work by seller’s quality department. What are you trying to do in this scenario?
Manage change control system for project
Procurement performance review
Inspection and Audit
Performance reporting
As per answer - Option B Procurement Performance Review
but in PMBOK page 498 the procurement review does not include review of quality audit (it includes analyze quality?) .
As I understand the PM is carrying out Inspection and Audit.
If you can please confirm.
Thanks