Re: Control Procurement

Post by manishpn » Wed Oct 28, 2020 9:32 pm

kashyap35 wrote:
Sat Oct 24, 2020 11:36 pm
This is from Izenbridge test

Question 17
1.00/0.00
You are a project manager and working with procurements for your projects. You are meeting seller to identify the performance of seller concerning SOW and also to see how work is getting performed. You are looking at quality audit documents created during execution of work by seller’s quality department. What are you trying to do in this scenario?

Manage change control system for project

Procurement performance review

Inspection and Audit

Performance reporting

As per answer - Option B Procurement Performance Review

but in PMBOK page 498 the procurement review does not include review of quality audit (it includes analyze quality?) .

As I understand the PM is carrying out Inspection and Audit.

If you can please confirm.

Thanks
Its a good question since the answer here may confuse you more, I will take this in clarification session o 31st October

Control Procurement

Post by kashyap35 » Sat Oct 24, 2020 11:36 pm

This is from Izenbridge test

Question 17
1.00/0.00
You are a project manager and working with procurements for your projects. You are meeting seller to identify the performance of seller concerning SOW and also to see how work is getting performed. You are looking at quality audit documents created during execution of work by seller’s quality department. What are you trying to do in this scenario?

Manage change control system for project

Procurement performance review

Inspection and Audit

Performance reporting

As per answer - Option B Procurement Performance Review

but in PMBOK page 498 the procurement review does not include review of quality audit (it includes analyze quality?) .

As I understand the PM is carrying out Inspection and Audit.

If you can please confirm.

Thanks