Re: Issues in managing scope

Post by manishpn » Mon May 03, 2021 12:58 am

pallav299 wrote:
Wed Apr 21, 2021 8:20 pm
A company is struggling to define the scope of a new project that has multiple phases with a high level of dependency between the phases.

How should the project manager approach this challenge?

A. Contract with a third-party company that specializes in helping businesses define scope of work on large projects.

B. Work with project stakeholders to recommend an iterative approach that will then help to define the project's scope.

C. Construct a project management plan that provides extra time within the schedule, then seek to revise the scope of work.

D. Suspend final delivery dates for the project in order to have time to revise the schedule once there is clarity on the scope of work.

The Correct Answer given is A and my answer is B . Having an iterative approach will help to to define high level scope and then things can be developed in small iterations . C and D is not making senses based on the given scenario. Question does not mentions if they have tight budget or enough money to Contract Third party company to define scope .So not sure how A becomes the right answer .

The question scenario mentions its multiphase project with heavy inter dependencies across phases, however we do not know if iterative will fit in to nature of the project, for e.g if its a construction project you cannot afford to learn from partially build structure and dismantle and build new from scratch.
Also we should focus on 'A company is struggling to define the scope ' so there is a help that organization (stakeholders) need in formulating the scope,

Issues in managing scope

Post by pallav299 » Wed Apr 21, 2021 8:20 pm

A company is struggling to define the scope of a new project that has multiple phases with a high level of dependency between the phases.

How should the project manager approach this challenge?

A. Contract with a third-party company that specializes in helping businesses define scope of work on large projects.

B. Work with project stakeholders to recommend an iterative approach that will then help to define the project's scope.

C. Construct a project management plan that provides extra time within the schedule, then seek to revise the scope of work.

D. Suspend final delivery dates for the project in order to have time to revise the schedule once there is clarity on the scope of work.

The Correct Answer given is A and my answer is B . Having an iterative approach will help to to define high level scope and then things can be developed in small iterations . C and D is not making senses based on the given scenario. Question does not mentions if they have tight budget or enough money to Contract Third party company to define scope .So not sure how A becomes the right answer .