The Project Manager is working with stakeholders for identifying requirements; one of the stakeholders asks to share the project schedule. What should the project manager do?


a. Explain that Project Schedule gets prepared after scope baseline

b. Share the project charter since it has the broad timelines

c. Prepare the schedule if not done already and share.

d. Share the Work Breakdown Structure



Please give the answer with a convincing explanation
manishpn
Expert
Expert
Posts: 3063
Joined: Sat Jan 04, 2014 3:55 pm

Re: Question

Sat Dec 12, 2020 7:53 pm

nipunverma wrote:
Sat Dec 12, 2020 4:46 pm
The Project Manager is working with stakeholders for identifying requirements; one of the stakeholders asks to share the project schedule. What should the project manager do?


a. Explain that Project Schedule gets prepared after scope baseline

This is the best answer

b. Share the project charter since it has the broad timelines

Sharing the entire PC can be an option but the question does not describe if the stakeholder should be receiving the PC, besides it has high level milestone which is not same as project schedule

c. Prepare the schedule if not done already and share.

Schedule preparation takes some time so this option is ruled out

d. Share the Work Breakdown Structure

WBS does not have schedule



Please give the answer with a convincing explanation
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
ni
nipunverma

Re: Question

Thu Apr 01, 2021 4:24 am

Thank you for replying.

I also marked the option (a) as correct answer.

But the correct answer given is (c).


Source: Izenbridge full syllabus 2 hr test.


Last bumped by Anonymous on Thu Apr 01, 2021 4:24 am.

Return to “PMP® Queries and Tips”

Who is online

Users browsing this forum: No registered users and 5 guests