Due to recent organizational changes, a number of project stakeholders are no longer with the company. What should the project manager do?
A. Update the communications management plan
B. Revise the project charter
C. Engage the project sponsor for replacements
D. Update the risk register
vi
vishita.veerabomma

Re: organization changes

Mon Dec 21, 2020 5:54 pm

what is the correct answer? My answer was C. but open to other suggestions/point of view
manishpn
Expert
Expert
Posts: 3063
Joined: Sat Jan 04, 2014 3:55 pm

Re: organization changes

Fri Jan 08, 2021 5:42 pm

vishita.veerabomma wrote:
Mon Dec 21, 2020 5:52 pm
Due to recent organizational changes, a number of project stakeholders are no longer with the company. What should the project manager do?
A. Update the communications management plan
B. Revise the project charter
C. Engage the project sponsor for replacements
D. Update the risk register

I think option D is the best option, stakeholders leaving organization may increase risk on the project, replacements may not be needed for all, but for some key stakeholders whose leaving has increased risk on the project


Last bumped by Anonymous on Fri Jan 08, 2021 5:42 pm.
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/

Return to “PMP® Queries and Tips”

Who is online

Users browsing this forum: Majestic-12 [Bot] and 5 guests