Practise test

Wed Sep 14, 2022 7:18 am

A project manager is using a suitability assessment tool to find the right project approach for a new project. The tool ranks on the following criteria: - Change: rate of change to requirements- Criticality: Criticality of product, processes and impact of defects - Buy-in: Executive support for adaptive methods - Team size: Number of members in project team- Team skill: Project team experience- Access: Direct collaboration/feedback with clients/sponsors Which combination of these factors would be best suited to a fully agile project approach?
0/1
Change: medium Criticality: high Buy-in: medium Team size: medium Team skill: high Access: high
Change: high Criticality: low Buy-in: high Team size: low Team skill: high Access: medium
Change: low Criticality: medium Buy-in: high Team size: low Team skill: medium Access: high
Change: low Criticality: low Buy-in: high Team size: medium Team skill: high Access: high


Posting again as not able to locate my last post on this one
User avatar
saket
Site Admin
Site Admin
Posts: 3544
Joined: Sat Dec 07, 2013 10:37 pm

Re: Practise test

Thu Sep 15, 2022 11:00 am

I found your old post using search option of this forum:
https://forum.izenbridge.com/viewtopic. ... ity#p44115