Harry has been assigned the flyover construction project and he is in the process of initiating the project. In order to meet the customer's project expectations, based on the business and compliance requirements, which of the following should Harry define FIRST?

High level scope of the project
Project schedule
Project Statement of Work
Product Statement of Work
ujjal_show
Super Member
Super Member
Posts: 1024
Joined: Thu Sep 17, 2015 12:59 pm

Re: Q-simplilearn

Sun Jan 03, 2016 2:10 pm

High level scope, because the project is in initiation phase and key word ".based on the business and compliance requirements"
User avatar
saket
Site Admin
Site Admin
Posts: 3120
Joined: Sat Dec 07, 2013 10:37 pm

Re: Q-simplilearn

Sun Jan 03, 2016 2:22 pm

In old PMBOK we did had term called high level scope , i follow elimination here


Project schedule : Can not it is too early

Project Statement of Work : should be given by customer as part of develop project charter process input

Product Statement of Work, no such term but if exists that also come from outside the project team.
Explore our online PMP Program , it makes PMP Easy :-) http://goo.gl/ZmD3xF

Image Image Image Image
sunildubai15
Contributor
Contributor
Posts: 229
Joined: Sun Nov 29, 2015 5:29 am

Re: Q-simplilearn

Mon Jan 04, 2016 7:34 am

Thanks Saket
this rule of elimination is very useful and helpful
favor
Posts: 2
Joined: Tue Dec 08, 2015 8:20 am

Re: Q-simplilearn

Mon Jan 04, 2016 7:30 pm

HI Saket,
just to be sure 'Project statement of work ' is the right answer?
User avatar
saket
Site Admin
Site Admin
Posts: 3120
Joined: Sat Dec 07, 2013 10:37 pm

Re: Q-simplilearn

Tue Jan 05, 2016 3:35 am

No, from available option "High level scope of the project" is the right answer because Project Statement of Work is not expected to be prepared by Project Manager it comes as an Input to him in Develop Project Charter Process.
Explore our online PMP Program , it makes PMP Easy :-) http://goo.gl/ZmD3xF