Unknown Unknown - Risk

Wed Jan 06, 2016 3:34 am

Hello Saket,

Can the Contingency Reserves be used for any unknow unknow? In case the know risk does not occur but if we forcee and unknow risk?
Can we use the contingency reserves?

Regards
Ramesh
arjun
Contributor
Contributor
Posts: 142
Joined: Thu Sep 10, 2015 3:50 am

Re: Unknown Unknown - Risk

Wed Jan 06, 2016 3:58 am

rameshsa@yahoo.com wrote:Hello Saket,

Can the Contingency Reserves be used for any unknow unknow? In case the know risk does not occur but if we forcee and unknow risk?
Can we use the contingency reserves?

Regards
Ramesh
Hi,

I think No and No. But i will wait for Saket to answer.

Thanks!
User avatar
saket
Site Admin
Site Admin
Posts: 3120
Joined: Sat Dec 07, 2013 10:37 pm

Re: Unknown Unknown - Risk

Wed Jan 06, 2016 4:59 am

See as per just contents for Unknown Unknown the management reserve is used. If you are using contingency reserve for it mean you had contingency planned for this even and it is known unkown.

Just keep simple in mind that for things which project manager and team could not plan for are covered in management reserve.
Explore our online PMP Program , it makes PMP Easy :-) http://goo.gl/ZmD3xF

Image Image Image Image
rameshsa@yahoo.com
Contributor
Contributor
Posts: 240
Joined: Thu Aug 20, 2015 5:18 am

Re: Unknown Unknown - Risk

Wed Jan 06, 2016 5:04 am

Hello Saket,

Let me put this like this... I have risk A (known unknown) and i have planned contingency reserve($1000)for that.
But Risk A (known unknown) did not occurs for some reasons.. Now I get Risk B (unknown unknown) in the project -- can I use the $1000 from contingency reserve to mitigate this risk B.?
User avatar
saket
Site Admin
Site Admin
Posts: 3120
Joined: Sat Dec 07, 2013 10:37 pm

Re: Unknown Unknown - Risk

Wed Jan 06, 2016 5:07 am

Yes you can since you have unused budget .
Explore our online PMP Program , it makes PMP Easy :-) http://goo.gl/ZmD3xF

Image Image Image Image
ujjal_show
Super Member
Super Member
Posts: 1024
Joined: Thu Sep 17, 2015 12:59 pm

Re: Unknown Unknown - Risk

Sat Jan 09, 2016 8:08 pm

if we follow Rita.. then it should not be.
User avatar
saket
Site Admin
Site Admin
Posts: 3120
Joined: Sat Dec 07, 2013 10:37 pm

Re: Unknown Unknown - Risk

Tue Jan 12, 2016 5:35 pm

:-) sometime we just need to take some judgement, we may not get very clear black and white guidelines. Anyway... following Rita is safer :)