Hi Experts,
I am confused between two answers B or C. Can you help finding correct answer with clarification? (Source - Oliver)
What is true for the process of scope validation?
A Insufficient documentation is not a reason to reject deliverables, as long as in all other respects they are built according to specifications agreed upon.
B The project team members must achieve acceptance of the deliverables. This process is coordinated and documented by the project management team.
C It is the project management team’s responsibility to obtain stakeholder’s formal acceptance of the completed project scope and deliverables.
D Formal acceptance will finally reconcile all inconsistencies among deliverables and documents that where caused by bad change control and scope creep.
Regards,
Vikram Unde
Q - Scope Validation
- ankurjig
- Contributor
Post
Re: Q - Scope Validation
I will choose C.
The reason will be the words 'formal acceptance of the deliverables from the stakeholders'.
It is not just acceptance of deliverables but formal acceptance or sign-off from the sponsor or customer that the project deliverables are as per the agreed requirements. This is similar to obtaining a User Acceptance Test (UAT) sign-off in software industry.
Ankur
The reason will be the words 'formal acceptance of the deliverables from the stakeholders'.
It is not just acceptance of deliverables but formal acceptance or sign-off from the sponsor or customer that the project deliverables are as per the agreed requirements. This is similar to obtaining a User Acceptance Test (UAT) sign-off in software industry.
Ankur
- manishpn
- Expert
- vikram_unde
- Contributor
Post
Re: Q - Scope Validation
Thanks Ankur!!ankurjig wrote:I will choose C.
The reason will be the words 'formal acceptance of the deliverables from the stakeholders'.
It is not just acceptance of deliverables but formal acceptance or sign-off from the sponsor or customer that the project deliverables are as per the agreed requirements. This is similar to obtaining a User Acceptance Test (UAT) sign-off in software industry.
Ankur
-
bi
Post
Re: Q - Scope Validation
Fine, I agree with the logic that 'Formal Acceptance' implies Option C. But what's wrong in Option B. There it is only 'Acceptance', so B should be equally valid choice.
Please suggest!
Please suggest!