Page 1 of 1

MANAGE STAKEHOLDER ENGAGEMENT - (EXECUTING )

Posted: Sat Nov 17, 2018 4:10 am
by krishnaiyer01
Hi,

Change request is one of the outputs of Manage Stakeholder Engagement. A change request may be as a result of changes to Project/Product Scope (PG 528 - PMBOK6).
If at all a Scope undergoes change , RISK will emerge .

Question: Why is not Risk Register Updated in this Processes. OR In case a RISK is identified at this stage, how should we proceed ? What steps should be followed .

Thanks

Krishnan

Re: MANAGE STAKEHOLDER ENGAGEMENT - (EXECUTING )

Posted: Mon Nov 19, 2018 11:35 am
by manishpn
krishnaiyer01 wrote:Hi,

Change request is one of the outputs of Manage Stakeholder Engagement. A change request may be as a result of changes to Project/Product Scope (PG 528 - PMBOK6).
If at all a Scope undergoes change , RISK will emerge .

Question: Why is not Risk Register Updated in this Processes. OR In case a RISK is identified at this stage, how should we proceed ? What steps should be followed .


Good point, while its not always necessary that a new risk will emerge eveytime we update scope, but in case it does it have to be analyzed like any other risks and update the risk register and other knowledge area as applicable.

Also remember PMBOK is not a rule book, so if one of the input or output is not mentioned in the book does not mean PM cannot have that.

Also at most (if you are unlucky) u will have 1-3 direct questions w.r.t IO or T and T in exam.

Thanks

Krishnan