Change request

Exclusive Forum for students to discuss PMP® queries and queries related to iZenBridge questions
sumitgoyal27
Participant
Participant
Posts: 63
Joined: Wed Jun 24, 2020 2:31 pm

Change request

Sat Aug 01, 2020 6:40 pm

You were monitoring one core stakeholder’s engagement level, and you found he was becoming neutral from supportive; you spoke to the stakeholder and found that he is not finding enough opportunity to engage with the project team, what should you do next?

Raise an issue.

Make changes in stakeholder engagement strategy documented in stakeholder engagement plan.

Raise a change request.

Call a meeting with your project team members.

Query:- Correct answer is B. However, IMO correct answer should be C because before changing pm plan we need to raise change request. Please respond.
manishpn
Expert
Expert
Posts: 2903
Joined: Sat Jan 04, 2014 3:55 pm

Re: Change request

Sat Aug 01, 2020 7:53 pm

sumitgoyal27 wrote:
Sat Aug 01, 2020 6:40 pm
You were monitoring one core stakeholder’s engagement level, and you found he was becoming neutral from supportive; you spoke to the stakeholder and found that he is not finding enough opportunity to engage with the project team, what should you do next?

Raise an issue.

Make changes in stakeholder engagement strategy documented in stakeholder engagement plan.

Raise a change request.

Call a meeting with your project team members.

Query:- Correct answer is B. However, IMO correct answer should be C because before changing pm plan we need to raise change request. Please respond.

Yes you are correct, in this case we need to first raise a Change request
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/

Return to “PMP® Exam Prep Questions”

Who is online

Users browsing this forum: No registered users and 3 guests