Kick Off Meeting

Sat Oct 24, 2020 7:28 pm

After the project charter is approved, a kick-off meeting is held. Six months into a project, the project team welcomes in new members and sets up another kick-off meeting. Three months later, a third kick-off meeting is held. One of the new team members asks why they are having a kick-off meeting after the project has been underway. What is the most-likely reason for a third kick-off meeting?
• Each time new team members are brought on a kick-off meeting is held.
• Kick-off meetings can be held at any convenient point in the project.
• The project is now entering a new phase.
• The project-sponsoring organization wants to welcome a new customer to the project team.

I choose option A, however the answer is option C. The question does not mention anything about entering new phase, so why is option C correct?
manishpn
Expert
Expert
Posts: 2975
Joined: Sat Jan 04, 2014 3:55 pm

Re: Kick Off Meeting

Wed Oct 28, 2020 9:37 pm

barath wrote:
Sat Oct 24, 2020 7:28 pm
After the project charter is approved, a kick-off meeting is held. Six months into a project, the project team welcomes in new members and sets up another kick-off meeting. Three months later, a third kick-off meeting is held. One of the new team members asks why they are having a kick-off meeting after the project has been underway. What is the most-likely reason for a third kick-off meeting?
• Each time new team members are brought on a kick-off meeting is held.
• Kick-off meetings can be held at any convenient point in the project.
• The project is now entering a new phase.
• The project-sponsoring organization wants to welcome a new customer to the project team.

I choose option A, however the answer is option C. The question does not mention anything about entering new phase, so why is option C correct?
Since you have confusion between A and C lets discuss that.
Agree that there is no mention of project entering into new phase,
However option A which says every time a new team members re onboarded a Kick off meeting is held is not true, if there is a sizeable number of Project team members onboarded and PM wants to have a kick off PM can, however its not mandatory.
Option C is not an ideal answer however form the choices given it is the best choice.

let me know if you have any doubts
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
manishpn
Expert
Expert
Posts: 2975
Joined: Sat Jan 04, 2014 3:55 pm

Re: Kick Off Meeting

Tue Nov 24, 2020 6:48 pm

barath wrote:
Sat Oct 24, 2020 7:28 pm
After the project charter is approved, a kick-off meeting is held. Six months into a project, the project team welcomes in new members and sets up another kick-off meeting. Three months later, a third kick-off meeting is held. One of the new team members asks why they are having a kick-off meeting after the project has been underway. What is the most-likely reason for a third kick-off meeting?
• Each time new team members are brought on a kick-off meeting is held.
• Kick-off meetings can be held at any convenient point in the project.
• The project is now entering a new phase.
• The project-sponsoring organization wants to welcome a new customer to the project team.

I choose option A, however the answer is option C. The question does not mention anything about entering new phase, so why is option C correct?
Since you have confusion between A and C lets discuss that.
Agree that there is no mention of project entering into new phase,
However option A which says every time a new team members re onboarded a Kick off meeting is held is not true, if there is a sizeable number of Project team members onboarded and PM wants to have a kick off PM can, however its not mandatory.
Option C is not an ideal answer however form the choices given it is the best choice.

let me know if you have any doubts


Last bumped by Anonymous on Tue Nov 24, 2020 6:48 pm.
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/