Change Request required for Project Docs ?

Sun Oct 25, 2020 10:49 am

Hi,

For a project if no info is provided about Configuration management plan (Implying that we do not know specifically which project document update requires CR), then can we assume that we can make changes to all project documents without a CR ?
Thanks,
Pranshul (Exam scheduled on 21-Nov) :roll:
Update - Passed the exam :D Thanks to all the educators and all the best to fellow test takers.
manishpn
Expert
Expert
Posts: 2972
Joined: Sat Jan 04, 2014 3:55 pm

Re: Change Request required for Project Docs ?

Tue Oct 27, 2020 7:54 am

pranshul.rawat wrote:
Sun Oct 25, 2020 10:49 am
Hi,

For a project if no info is provided about Configuration management plan (Implying that we do not know specifically which project document update requires CR), then can we assume that we can make changes to all project documents without a CR ?

No , usually all project document and PMP are version controlled.
PMBOK6 explicitly mentioned need to CR for making such changes , in PMP it may be mentioned that Project Manager has the authority to make such changed without going to CCB but CR will be needed
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/