Project communications

Exclusive Forum for students to discuss PMP® queries and queries related to iZenBridge questions
im_avneesh
Posts: 12
Joined: Wed Oct 28, 2020 1:10 pm

Project communications

Sat Oct 31, 2020 4:45 pm

Phill is leading a project where due to change in Business Conditions, stakeholders have become very involved in the project. As a result, Phil started getting unexpected requests from his stakeholders about the project progress. He wants to respond with the information which can help stakeholders to make decisions for the project. All of the following can be used by Phil to respond to their requests EXCEPT:

Communications management plan to know stakeholder’s communication requirements, structure, and distribution, etc.

The Stakeholder Register to know about stakeholders who need information about project progress.

Organizational process assets to know the format and template which can be used

Work performance reports communicating the project progress
manishpn
Expert
Expert
Posts: 2975
Joined: Sat Jan 04, 2014 3:55 pm

Re: Project communications

Sun Nov 01, 2020 9:22 pm

refer to previous discussion,

although I agree this is not a good questions, please write to support@izenbridge and ask them to rectify

viewtopic.php?f=11&t=18180&p=39353&hili ... ect#p39353



viewtopic.php?f=11&t=11821&p=32685&hili ... ect#p32685
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/