No direct relationship between tasks.

Mon May 03, 2021 6:47 pm

A new product development project has the following characteristics:

-There are three main tasks.
-Task A must be delivered 4 weeks before task C starts.
-Once task B is finished; task C will start.

What is the relationship between tasks A and B?

A. Finish-to-start (FS)

B. Finish-to-finish (FF)

C. Start-to-start (SS)

D. Start-to-finish (SF)

Given answer is B and mine is A. Since there is no direct relationship between task A and task B , how can we define relationship? All we know is that both should be completed before C starts. There is no numerical time for B completion given that will help us to define out of task A and task B which will start/finish when .
manishpn
Expert
Expert
Posts: 3062
Joined: Sat Jan 04, 2014 3:55 pm

Re: No direct relationship between tasks.

Wed May 05, 2021 7:19 pm

I recommend that you draw a SND and upload the picture
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/