September 19th 2020 , PMP Clarification @ 7:00 PM IST

One spot to pull in the announcement of exclusive webinar and to post further doubts and queries
srishti
Posts: 17
Joined: Tue Feb 04, 2020 6:39 am

September 19th 2020 , PMP Clarification @ 7:00 PM IST

Thu Sep 10, 2020 10:05 am

Use this thread to post your queries, we will discuss in the Webinar.

Day/Date:- Sat/September 19th, 2020

Time:- 7:00 - 8:00 PM IST + 5:30 GMT

This session will be taken by Manish Panchmatia


Get Registered: https://us02web.zoom.us/meeting/registe ... bOlWTIrl4B

Regards
Srishti
ks
ksabhi01@yahoo.com

Re: September 19th 2020 , PMP Clarification @ 7:00 PM IST

Sat Sep 19, 2020 4:36 am

1-Team is working on Project ABC. In the second month of the project, Tim and Steve found that both of them working on the same work. This situation could have been avoided by having proper?
a. RAM
b. Project Organization Structure
c. Status meetings
d. Matrix organization

Answer and detailed explanation:

2-Lucy has to brief her key project stakeholders on the recent
approved changes to the project scope. Which of the following
project documents will provide essential input to Lucy for
preparing her presentation?
A- Change request form
B- Change control procedures
C- Change log
D- Issue management procedures

Ans-C Please explain.

3-A project to migrate an Organization's email system to another platform creates an unexpected, but significant issue on another business critical system. What should the project manager do?

Ask the project team to resolve the issue

Inform the stakeholders of the issue

Update the issue log

Revise the project management plan to include the issue

Answer-B Please explain
ar
arvind

Re: September 19th 2020 , PMP Clarification @ 7:00 PM IST

Sat Sep 19, 2020 1:32 pm

Q. During project planning, the project team rigorously defined project scope. During project execution, a senior engineer calls the project manager and suggests a simpler and more efficient design which could benefit the project.
What should project manager do next?
A. Nothing, no changes are needed since the project scope was rigorously defined
B. Discuss the change with project sponsor
C. Evaluate the impact of proposed change on the project constraints
D. Ask that the engineer submit a change request
Correct answer mentioned as D. (concerned in between answer C and D. please explain)
balakrishnan_2020
Posts: 3
Joined: Mon May 25, 2020 7:51 pm

Re: September 19th 2020 , PMP Clarification @ 7:00 PM IST

Sat Sep 19, 2020 1:57 pm

You are in the closing stage of a global project. Your stakeholders are located in different countries, and have different backgrounds, which often leads to communication problems. Which interpersonal and team skill technique would have helped you the most for global stakeholders?

A. Communication Style Assessment
B. Political Awareness
C. Cultural Awareness
D. Communication Competence

Answer & Explain
indrani_deka
Posts: 8
Joined: Tue Aug 04, 2020 10:18 am

Re: September 19th 2020 , PMP Clarification @ 7:00 PM IST

Tue Sep 22, 2020 7:02 am

Here is the link of Clarification Session of 19th Sep 2020