Re: November 28th 2020 , PMP Clarification @ 7:00 PM IST
Do we need to study the Agile planning for this year 2020 PMP test? also does the series of videos cover everything needed to clear the exam? or is it just a refresher
- Victor
- Beginner
Post
Re: November 28th 2020 , PMP Clarification @ 7:00 PM IST
Can the PM approve the CR if it does not impact any Project Performance Baseline? (Scope, Schedule and Cost Baseline)
- Victor
- Beginner
Post
Re: November 28th 2020 , PMP Clarification @ 7:00 PM IST
Question 23
You need sensor technology for your project. During planning, you have identified that these sensors can be imported from China or can also be manufactured in house. To manufacture in house, you would need to invite samples from China. Also, the experienced and skilled resources in your organization are currently busy in other projects, would be available in a few months and there are some fresher’s available in the resource pool who could be utilized but will need to undergo some training. You want to finalize a schedule for this project. Which of the following would be the best way to design a schedule for this project considering all the scenarios mentioned above?
a Use a simulation technique to model the various scenarios to calculate possible schedule outcome.
b Draw a network diagram, and then use lead and lag to refine the schedule.
c Refer to the past project documentation to see how you had scheduled and what were the lessons learned.
d Draw a network diagram for various scenarios, assess the feasibility of the schedule under different conditions, and see how the schedule aligns with the project objectives.
Right Answer is A
I answered it as c considering the indications i see from the questions:
1) can also be manufactured in house,
2) there are some fresher’s available in the resource pool who could be utilized but will need to undergo some training. You want to finalize a schedule for this project
Also considering that referring to the OPA would be the 1st step before i do the simulation.
You need sensor technology for your project. During planning, you have identified that these sensors can be imported from China or can also be manufactured in house. To manufacture in house, you would need to invite samples from China. Also, the experienced and skilled resources in your organization are currently busy in other projects, would be available in a few months and there are some fresher’s available in the resource pool who could be utilized but will need to undergo some training. You want to finalize a schedule for this project. Which of the following would be the best way to design a schedule for this project considering all the scenarios mentioned above?
a Use a simulation technique to model the various scenarios to calculate possible schedule outcome.
b Draw a network diagram, and then use lead and lag to refine the schedule.
c Refer to the past project documentation to see how you had scheduled and what were the lessons learned.
d Draw a network diagram for various scenarios, assess the feasibility of the schedule under different conditions, and see how the schedule aligns with the project objectives.
Right Answer is A
I answered it as c considering the indications i see from the questions:
1) can also be manufactured in house,
2) there are some fresher’s available in the resource pool who could be utilized but will need to undergo some training. You want to finalize a schedule for this project
Also considering that referring to the OPA would be the 1st step before i do the simulation.
- Victor
- Beginner
Post
Re: November 28th 2020 , PMP Clarification @ 7:00 PM IST
Question 26
Your development team has worked closely with customer and successfully developed incrementally and iteratively. The customer is now using all developed functionalities. Which of the following options would indicate that it is now time to close the project and transfer the complete ownership of the deliverables to Steven?
a When all the features in the roadmap have been developed, the project is ready to be closed.
b When there are no new value additions being made to the system.
c When customer says that the project is now complete and he does not want any new features.
d When the contract deadline has arrived.
What will be the right Answer to this ?
Your development team has worked closely with customer and successfully developed incrementally and iteratively. The customer is now using all developed functionalities. Which of the following options would indicate that it is now time to close the project and transfer the complete ownership of the deliverables to Steven?
a When all the features in the roadmap have been developed, the project is ready to be closed.
b When there are no new value additions being made to the system.
c When customer says that the project is now complete and he does not want any new features.
d When the contract deadline has arrived.
What will be the right Answer to this ?
- Victor
- Beginner
Post
Re: November 28th 2020 , PMP Clarification @ 7:00 PM IST
Question 27
You are a project manager to transport 200 boxes of perishable frozen foods through Airplane’s frozen cargo compartment. You have observed that your shipment is outside the frozen trucks and the frozen airplane compartments for more than recommended time. Which of the following options would you first implement to ensure that such a scenario does not happen again and also that you upload your lessons learned on the OPA, once you have devised a corrective action?
Discuss this shipment requirement with a specialist
Do a root cause analysis
Do a cost-benefit analysis
Do alternative analysis
The answer is "Do alternative analysis"
I had selected the answer as "Do a root cause analysis" considering that it is mentioned in the question as "such a scenario does not happen again and also that you upload your lessons learned on the OPA, once you have devised a corrective action"
You are a project manager to transport 200 boxes of perishable frozen foods through Airplane’s frozen cargo compartment. You have observed that your shipment is outside the frozen trucks and the frozen airplane compartments for more than recommended time. Which of the following options would you first implement to ensure that such a scenario does not happen again and also that you upload your lessons learned on the OPA, once you have devised a corrective action?
Discuss this shipment requirement with a specialist
Do a root cause analysis
Do a cost-benefit analysis
Do alternative analysis
The answer is "Do alternative analysis"
I had selected the answer as "Do a root cause analysis" considering that it is mentioned in the question as "such a scenario does not happen again and also that you upload your lessons learned on the OPA, once you have devised a corrective action"
- Victor
- Beginner
Post
Re: November 28th 2020 , PMP Clarification @ 7:00 PM IST
Need guidance to build endurance to give 200 question, i tried to attempt a short mock of 100 question but only managed to reach finish 71 questions.
- Victor
- Beginner
Post
Re: November 28th 2020 , PMP Clarification @ 7:00 PM IST
Question 51
1
You are the product owner of a conference ticket booking online application which will be developed in 5 iterations. The first iteration development is in progress. The goal of the first iteration is to enable user registration followed by the collection of conference fees to start generating revenue.
One of the stakeholders has requested you to change the flow of the user registration process such that payment is collected first and then user information is collected. The stakeholder feels that this will attract only serious users to register. As the product owner, which of the following options will be most appropriate to implement in such a situation?
A You will generate a change request
B You will implement the changes in the software to deliver value
C You will defer the changes till the next increment.
D You will conduct an impact analysis of how much waste will be generated if this change is implemented.
the right answer is C and i want to know why it cant be D
1
You are the product owner of a conference ticket booking online application which will be developed in 5 iterations. The first iteration development is in progress. The goal of the first iteration is to enable user registration followed by the collection of conference fees to start generating revenue.
One of the stakeholders has requested you to change the flow of the user registration process such that payment is collected first and then user information is collected. The stakeholder feels that this will attract only serious users to register. As the product owner, which of the following options will be most appropriate to implement in such a situation?
A You will generate a change request
B You will implement the changes in the software to deliver value
C You will defer the changes till the next increment.
D You will conduct an impact analysis of how much waste will be generated if this change is implemented.
the right answer is C and i want to know why it cant be D
- Victor
- Beginner
Post
Re: November 28th 2020 , PMP Clarification @ 7:00 PM IST
You are a project manager to manufacture scientific devices. You are planning a project to deliver devices in various shapes, sizes, and with other couples of parameters. You have delivered many orders in the past where there were individual requirements of either shape or size or design but not order with all these variations at once. What would be the most important action to help finalize the approach for this project?
Invite an external consultant who has experience executing such orders
Refer to the past project documents including lessons learned documents
You will try to optimize the time taken to execute the order by analyzing the enterprise environmental factors.
Conduct a meeting with your project team and think collectively about various ways of executing this order.
What should be the correct answer?
Invite an external consultant who has experience executing such orders
Refer to the past project documents including lessons learned documents
You will try to optimize the time taken to execute the order by analyzing the enterprise environmental factors.
Conduct a meeting with your project team and think collectively about various ways of executing this order.
What should be the correct answer?
Post
Re: November 28th 2020 , PMP Clarification @ 7:00 PM IST
How to map & relate the tasks from exam content outline to PMBOK content (to see in detail sub tasks & involved processes).
- jyotimayank
- Expert
Post
Questions by Rajeshwari
1. What is the last step – Release Resources or Party?
2. Can we say our project closed though our payment is not yet received from our customer for our work completed, customer accepted deliverable, signed off?
3. If we take the test from home, do we get 10 mins break? Is that included or excluded in the 4 hours?
4. If we take the exam from home, do we get the results immediately or after 2 days?
2. Can we say our project closed though our payment is not yet received from our customer for our work completed, customer accepted deliverable, signed off?
3. If we take the test from home, do we get 10 mins break? Is that included or excluded in the 4 hours?
4. If we take the exam from home, do we get the results immediately or after 2 days?
Jyoti Gupta
PMP Mentor & Coach
iZenbridge Consultancy Pvt Ltd
PMP Mentor & Coach
iZenbridge Consultancy Pvt Ltd