kanban : buffer size

Exclusive forum for iZenBirdge PMI-ACP® clients
brijesh.shah
Participant
Participant
Posts: 57
Joined: Sat Aug 27, 2016 8:24 am

kanban : buffer size

Wed Jan 04, 2017 3:25 am

What is the buffer size in kanban ? Kindly help me to understand and elaborate.
seema.sonkiya
Expert
Expert
Posts: 2486
Joined: Fri Jul 11, 2014 11:57 am

Re: kanban : buffer size

Wed Jan 04, 2017 10:22 am

The buffer size is not the standard term in the kanban. Can you describe the context of the question?
brijesh.shah
Participant
Participant
Posts: 57
Joined: Sat Aug 27, 2016 8:24 am

Re: kanban : buffer size

Fri Jan 06, 2017 5:29 am

You are project Manager and have been participating in initial discussion with product Managers, business and architect team to reach an agreement on work in progress limit for your team. After analyzing the nature of work and other parameters you have proposed a Work in progress limit of 50 however Business stakeholders want WIP in progress limit to be increased to 75 as there is need to faster time to market. As a Project manager what are the factors you should consider before deciding on WIP limits

Work Items per team member will help determine WIP limits

WIP limits is influenced by Queue and buffer size , both of these needs to be determined before the start of the project to determine an accurate WIP Limit

WIP limits are mostly influenced by Queue size and needs to be determined during the course of the project as more information is available to team

WIP limits is influenced by Queue and buffer size , both of these needs to be empirically adjusted as required as the project progresses
- Solution
WIP limit is influenced by Queue and buffer size, however it is not recommended to arrive at an accurate WIP and potentially delay the rollout of the project, recommended approach is to empirically adjust through observations.

I found the term in this question...
User avatar
saket
Site Admin
Site Admin
Posts: 3120
Joined: Sat Dec 07, 2013 10:37 pm

Re: kanban : buffer size

Fri Jan 06, 2017 9:57 am

it will be better to know what is Buffers in Kanban .

Say we have stages , like Pending, doing , waiting for UAT, UAT , done.

Now waiting for UAT , is a stage you do not apply WIP Limit and you say even infinite things can stay there, since you keep working and schedule UAT when you have some items at this stage, this is called Buffer. Now when we say Buffer size it could mean we want to Limit number of items stay in buffer and we do something about it once it reach that limit, Say you make 10 in case of this, it mean when you have 10 items waiting for UAT, you should get the UAT Done . Que are same but at input point, say pending stage, you may want keep recording new work as you get in que stage and do not apply WIP Limit.
Explore our online PMP Program , it makes PMP Easy :-) http://goo.gl/ZmD3xF