Your organization has a rule of decomposition of the work breakdown structure at a level, where the work can be done in less than a week; you planned to change this to a month for your project, what would you do next?

A. Inform the team about it
B. Request for tailoring
C. Prepare the Scope Management Plan with a one-month level WBS
D. Raise a Change Request

So the question asks what you do when you plan to modify your Organization Project Management Process.

Can you directly go ahead and plan as per your understanding of the project need?

If you think yes, you can be looking to select one of the following options
A. Inform the team about it
C. Prepare the Scope Management Plan with a one-month level WBS

We don't think that the Project Manager can decide on his own about the process; he is expected to work with stakeholders and ask for agreement. So we look at the other two options
B. Request for tailoring
D. Raise a Change Request

Tailoring is necessary because each project is unique; and it should address the competing constraints of scope, cost, etc. The issue is about process customization.