PMP micro learning videos Series - PMP Free Question 27 : Common understanding on final acceptance

Posted: Wed May 01, 2019 8:50 am
by jyotimayank
You have recently joined the ongoing project, and discover that stakeholders are not having a common understanding of the process to get formal acceptance of completed deliverables, what would you do next?

A. Call a meeting with stakeholders
B. Meet the team and discuss
C. Meet the last project manager and ask
D. Check the scope management plan

All options are possible action the project manager may take; we need to find which action the project manager should consider first.

Talking to Stakeholders and team is a good idea, but the project manager should know about the current process.
What is the first thing the Project Manager should do to know the current process and gaps in it?

Many may think it’s a good idea to talk to the past project manager, but should not you look at the current process in the Scope Management Plan before you speak to the previous project manager.

Watch this video for the correct answer.