Requirement stage VS requirement status

Discuss PMI-PBA® doubts, tips and lesson learned. Master the art of Business analysis with iZenBridge
hvlani85
Posts: 3
Joined: Tue Sep 28, 2021 3:21 pm

Requirement stage VS requirement status

Mon Nov 08, 2021 9:55 am

Hello,

In the « requirement life cycle » video, the terms « stage » and « status » seem to be used interchangeably. Is it correct? Do they have the same meaning or should we be careful as they refer to different things?

Thank you
User avatar
saket
Site Admin
Site Admin
Posts: 3317
Joined: Sat Dec 07, 2013 10:37 pm

Re: Requirement stage VS requirement status

Mon Nov 08, 2021 10:27 am

Yes it may look interchangeable, the STAGE is an important element and it usually represents the WORKFLOW stage of a given requirement.
Say, it is an Analysis, develops etc

The Status can be something generic, it can get things like On HOLD, Completed, Deferred etc, it possible that the requirement reaches to Dev Stage and get on HOLD.