Clarification for Issue Log

Discuss PMP doubts, tips and lesson learned. iZenBridge makes PMP® Certification easy
binesh007
Posts: 5
Joined: Wed Feb 05, 2020 5:37 am

Clarification for Issue Log

Wed Feb 05, 2020 7:43 am

When we need to log an issue in the issue log?
What are all the criteria?
Can we log internal team issues/ conflicts in the issue log?
Do we need to log personal issues of a team member which can affect the performance of project.
manishpn
Expert
Expert
Posts: 2903
Joined: Sat Jan 04, 2014 3:55 pm

Re: Clarification for Issue Log

Wed Feb 05, 2020 9:24 pm

binesh007 wrote: When we need to log an issue in the issue log?
We need to register all issues in issue log as long as it not sensitive and should be restricted to select few stakeholder


What are all the criteria?

There are no specific criteria, it depends on how important is the issue and its potential impact on the project

Can we log internal team issues/ conflicts in the issue log?
Usually no if it has to mention names , PM has to be pragmatic in this regards

Do we need to log personal issues of a team member which can affect the performance of project.
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
binesh007
Posts: 5
Joined: Wed Feb 05, 2020 5:37 am

Re: Clarification for Issue Log

Fri Feb 07, 2020 4:00 pm

Thank you so much Mr. Manish for your valuable reply. I had encountered through a question asking...

If a key team member planned for a leave and he noticed in project schedule that during his absence (planned leave) some critical activities are planned which is assigned for him. Since it is a specialist job, there is no other to replace him. He cannot postpone the leave. He report this to PM. As a PM what should he do? Options are:

A. Inform Management
B. Log the issue in issue log
C. Inform Sponsor

I dont remember the last option. I think it was irrelevant.
manishpn
Expert
Expert
Posts: 2903
Joined: Sat Jan 04, 2014 3:55 pm

Re: Clarification for Issue Log

Sat Feb 15, 2020 12:57 pm

binesh007 wrote:Thank you so much Mr. Manish for your valuable reply. I had encountered through a question asking...

If a key team member planned for a leave and he noticed in project schedule that during his absence (planned leave) some critical activities are planned which is assigned for him. Since it is a specialist job, there is no other to replace him. He cannot postpone the leave. He report this to PM. As a PM what should he do? Options are:

A. Inform Management
B. Log the issue in issue log
C. Inform Sponsor

I dont remember the last option. I think it was irrelevant.
ok , can you attempt on what should be the correct option
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
Victor
Posts: 10
Joined: Fri Mar 15, 2019 1:54 pm

Re: Clarification for Issue Log

Thu Mar 12, 2020 12:00 am

Opion B "Log the issue in issue log" will be the correct answer?