Change Request

Posted: Wed Feb 05, 2020 1:54 pm
by binesh007
You are currently performing a monitoring and controlling project activity, and you have discovered that some of the project work has not been performed according to the plan. If these issues are not fixed before the next customer inspection, your project might be cancelled. You have analysed the situation, and the corrective action will only require a minor adjustment to a configuration element. What should you do first?
A. Implement the corrective actions
B. Submit a change request
C. Consult the project sponsor
D. Delay the scheduled customer inspection

Re: Change Request

Posted: Wed Feb 05, 2020 9:35 pm
by manishpn
binesh007 wrote:You are currently performing a monitoring and controlling project activity, and you have discovered that some of the project work has not been performed according to the plan. If these issues are not fixed before the next customer inspection, your project might be cancelled. You have analysed the situation, and the corrective action will only require a minor adjustment to a configuration element. What should you do first?
A. Implement the corrective actions
B. Submit a change request
C. Consult the project sponsor
D. Delay the scheduled customer inspection

It has to be option #2, refer to section 4.5.3.2 in PMBOK

Re: Change Request

Posted: Fri Feb 07, 2020 3:24 pm
by binesh007
Thanks for your kind reply. In question it is mentioned that "you discovered that some of the project work has not been performed according to the PLAN. My doubt is why we need CR to perform something which was already in the plan and missed to implement it. As per my understanding CR is used to implement if there is a change from any plan or baselines. Can you please clarify?

Re: Change Request

Posted: Sat Feb 15, 2020 11:14 am
by manishpn
binesh007 wrote:Thanks for your kind reply. In question it is mentioned that "you discovered that some of the project work has not been performed according to the PLAN. My doubt is why we need CR to perform something which was already in the plan and missed to implement it. As per my understanding CR is used to implement if there is a change from any plan or baselines. Can you please clarify?

good catch , and yes I agree that if the original scope is to be delivered you dont need a CR, however since you need to perform corrective action as mentioned in the question, and corrective action is not part of original scope hence you need a CR