forum-pin-post

Crashing Activity

Discuss PMP doubts, tips and lesson learned. iZenBridge makes PMP® Certification easy
bhawna05
Posts: 4
Joined: Fri May 29, 2020 9:31 am

Crashing Activity

Mon Jul 13, 2020 2:56 pm

Hi Manish,

I missed last webinar where I Put this question.

Baseline Crash
activity time cost time cost
A 10 4000 8 6000
B 2 6000 2 6000
C 14 22000 12 26000
D 6 9000 5 10000
E 9 14000 7 19000
F 8 18000 4 36000


Not able to paste excel table neither I could attach the excel file hence, I don't know how to post?




column 1 is activity
column 2 and 3 is Baseline which has two sub coloumn time and cost
Coulmn 4 is Crash having sub coloum of time cost

Using this chart, whihc is the lowest cost of crashing the project to save 4 weeks?

If you are not able to understand the question, tell me the way I will do that. I dont think it requires network diagram.
manishpn
Expert
Expert
Posts: 2883
Joined: Sat Jan 04, 2014 3:55 pm

Re: Crashing Activity

Wed Jul 29, 2020 10:07 pm

bhawna05 wrote:
Mon Jul 13, 2020 2:56 pm
Hi Manish,

I missed last webinar where I Put this question.

Baseline Crash
activity time cost time cost
A 10 4000 8 6000
B 2 6000 2 6000
C 14 22000 12 26000
D 6 9000 5 10000
E 9 14000 7 19000
F 8 18000 4 36000


Not able to paste excel table neither I could attach the excel file hence, I don't know how to post?




column 1 is activity
column 2 and 3 is Baseline which has two sub coloumn time and cost
Coulmn 4 is Crash having sub coloum of time cost

Using this chart, whihc is the lowest cost of crashing the project to save 4 weeks?

If you are not able to understand the question, tell me the way I will do that. I dont think it requires network diagram.
Please take a picture of the question on the screen and upload
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/