Page 1 of 1

Calculate ES for Activity G in the given network diagram

Posted: Sun Sep 19, 2021 7:01 pm
by cs09rajesh
Hi,

Anyone can explain here for the below queries
Calculate ES for Activity G in the given network diagram

Re: Calculate ES for Activity G in the given network diagram

Posted: Sun Sep 19, 2021 7:09 pm
by cs09rajesh
It's cleared now.

Thanks!

Re: Calculate ES for Activity G in the given network diagram

Posted: Mon Sep 20, 2021 9:46 am
by saket
Good you got it, as of now we are not finding people getting this much detailed questions on Schedule in exam, so you may not spend time on such questions for PMP exam.