A project manager has been asked to conduct a risk analysis that is based on a high-level scope. As part of the analysis, the project manager must use expert judgment to prepare a document. Which document-based action is being performed?
Preparing the scope statement document
Creating the project charter
Creating a project management plan
Documenting the risk management plan
How is the answer here as Project Charter? Pls clarify
Moc test
- saket
- Site Admin
Post
When you are performing risk analysis based on high level scope and using expert judgement (mean you do not have any other doc to refer to) which document you might be making or supporting.
I see not a good question though, but options make it clear to find right answer
A.Preparing the scope statement document
You make scope based on requirement and focus is not on risk
C. Creating a project management plan
No intention of making plan rather asking where to record high level risks
D.
Documenting the risk management plan
Risk Management Plan does not contain risks, rather it contains approach to handle risk
Re: Moc test
The above is core of question asking.A project manager has been asked to conduct a risk analysis that is based on a high-level scope. As part of the analysis, the project manager must use expert judgment to prepare a document.
When you are performing risk analysis based on high level scope and using expert judgement (mean you do not have any other doc to refer to) which document you might be making or supporting.
I see not a good question though, but options make it clear to find right answer
A.Preparing the scope statement document
You make scope based on requirement and focus is not on risk
C. Creating a project management plan
No intention of making plan rather asking where to record high level risks
D.
Documenting the risk management plan
Risk Management Plan does not contain risks, rather it contains approach to handle risk