Ques. A particular stakeholder has been requesting many changes in your project scope, you realized this stakeholder was not involved in collect requirement process, this could have happened because of _________________

a) Wrong classification of this stakeholder during identify stakeholders process
b) Not identifying this stakeholder in Project Charter
c) Not including activities to Interview this stakeholder in Activity List
d) Not identify risk of not involving this stakeholder in risk register

QUERY : What would be correct Answer ? (a) or (b)
AM1969
Contributor
Contributor
Posts: 194
Joined: Fri Dec 05, 2014 7:05 pm

Re: Stakeholder Management

Sat Aug 01, 2015 5:26 pm

answer B according to me...
let me know if I am wrong.
Last edited by AM1969 on Sat Aug 01, 2015 6:30 pm, edited 1 time in total.
RAVI-GUPTA
Posts: 3
Joined: Thu Jun 25, 2015 4:05 am

Re: Stakeholder Management

Sat Aug 01, 2015 5:41 pm

Well noted . .

This Question is from QUAMPUS where answer is (A) with explanation:
"This problem is related to stakeholder classification, you have not properly classified this stakeholder and that is why you are getting his feedback at later stages."

Plz suggest. . .
AM1969
Contributor
Contributor
Posts: 194
Joined: Fri Dec 05, 2014 7:05 pm

Re: Stakeholder Management

Sat Aug 01, 2015 5:54 pm

sorry,I was wrong . Please ignore.
pank_pmp
Super Member
Super Member
Posts: 489
Joined: Tue Aug 05, 2014 11:04 am

Re: Stakeholder Management

Mon Aug 03, 2015 4:18 am

Answer A is more close. B cannot be true since you do not necessarily identify all stakeholders during Project charter creation.