doubt regarding EVM

Mon Jan 04, 2016 4:44 am

Q1.
How to correlate behind budget and ahead budget with under,over budget? First two words are confusing.
Q2.
In question it is asked to calculate EAC. answer is coming 349.6
choices are 349 and 350
which one to choose?
answer is 349. but it should be rounded up and 350.
sunildubai15
Contributor
Contributor
Posts: 229
Joined: Sun Nov 29, 2015 5:29 am

Re: doubt regarding EVM

Mon Jan 04, 2016 7:30 am

Ans 1
behind and ahead is term for schedule
kindly post the complete question for question 2
skmpmp_2015
Beginner
Beginner
Posts: 36
Joined: Sat Oct 17, 2015 2:27 am

Re: doubt regarding EVM

Tue Jan 05, 2016 1:17 am

1. In few questions of quampus ahead and behind terms were used for budget. pl clarify how they are related to under and over?
2. If a result is coming as 349.6 and options are 349 and 350. Which one to select?
ujjal_show
Super Member
Super Member
Posts: 1024
Joined: Thu Sep 17, 2015 12:59 pm

Re: doubt regarding EVM

Tue Jan 05, 2016 6:30 pm

ahead of budget = under budget = CPI >1
behind budget = over budget = CPI < 1
on budget = CPI =1

2. If a result is coming as 349.6 and options are 349 and 350. Which one to select?
don't worry about this in real exam you will never find this kind of issue.
skmpmp_2015
Beginner
Beginner
Posts: 36
Joined: Sat Oct 17, 2015 2:27 am

Re: doubt regarding EVM

Wed Jan 06, 2016 2:13 am

thanks