Regarding control communication

Sat Jan 09, 2016 5:41 am

"Control communication is the process of monitoring and control communications to ensure the information needs of the project stakeholders are met."
For the above tasks we need to check first list of stakeholders to whom communications were done. So stakeholder register should be an input to this process. Pl comment.
ujjal_show
Super Member
Super Member
Posts: 1024
Joined: Thu Sep 17, 2015 12:59 pm

Re: Regarding control communication

Sat Jan 09, 2016 7:11 pm

Project management plan is input to control communication,, Project management plan contain the Communications management plan. Stakeholder register is input to Communications management plan, contains the following information, which is extracted from Stakeholder register

• Person responsible for communicating the information;
• Person responsible for authorizing release of confidential information;
• Person or groups who will receive the information;

in simple, the Stakeholder information (Stakeholder register) is input to control communication through Project management plan