Hello,

While the development team is busy in executing the sprint; the product owner will work on prioritizing the product backlogs. But if he needs to come up with the costing involved to develop the user story then how can he utilize the current development team? & can we show that time as a lag in the current sprint execution.

Regards......
Rohit
seema.sonkiya
Expert
Expert
Posts: 2636
Joined: Fri Jul 11, 2014 11:57 am

Re: Product Backlog Prioritization

Fri Mar 12, 2021 5:20 am

There is no need of lag in current sprint execution. Team and PO sees how much time is needed to refine the backlog and estimation. The team reserves time for it within Sprint.

Scrum guide say on an average 10% of Sprint time goes in such activities.
rwalimbe
Posts: 3
Joined: Fri Dec 25, 2020 10:46 am

Re: Product Backlog Prioritization

Sat Mar 13, 2021 5:48 pm

Hi Seema,

Thanks a lot for your inputs.

Can we say, that the developers needs to make sure to include 10% + Sprint efforts while doing the sprint planning?

Thanks & Regards
Rohit Walimbe
seema.sonkiya
Expert
Expert
Posts: 2636
Joined: Fri Jul 11, 2014 11:57 am

Re: Product Backlog Prioritization

Sun Mar 14, 2021 3:13 pm

Yes, 10% is just a recommendation in Scrum Guide. PO, SM and developers makes sure that a enough time is allotted to backlog refinement and estimation.
rwalimbe
Posts: 3
Joined: Fri Dec 25, 2020 10:46 am

Re: Product Backlog Prioritization

Mon Mar 15, 2021 2:37 pm

Hi Seema,

Thanks a lot for your input & the clarification.