59. You recently assigned staff members to activities, estimated work and scheduled your project. You then created the following resource histogram for your staff:

What does this diagram tell you? 59
o The project can probably not be finished as scheduled.
o You may be able to finish the project early by reassigning work.
o You should avoid network logic diagramming for scheduling.
o You may run into problems with dual reporting relationships.

YOU need to look at histogram i m not able to paste ..plz answer .. explain.
thiru26@gmail.com
Contributor
Contributor
Posts: 242
Joined: Sun Sep 13, 2015 10:57 pm

Re: Oliver 175 - 59th Question

Thu Oct 22, 2015 1:00 am

Use snipping tool to capture the diagram and then upload here in the forum.
ujjal_show
Super Member
Super Member
Posts: 1024
Joined: Thu Sep 17, 2015 12:59 pm

Re: Oliver 175 - 59th Question

Thu Oct 22, 2015 10:20 am

Take the screen shoot ->pest in paint -> save the pic -> upload as below.
Attachments
Untitled.jpg
Untitled.jpg (27.66 KiB) Viewed 7927 times
vivek3377
Super Member
Super Member
Posts: 391
Joined: Thu Sep 10, 2015 2:32 am

Re: Oliver 175 - 59th Question

Fri Oct 23, 2015 4:21 pm

Still, since question refers to Resource Histogram, I would go for option
o You may be able to finish the project early by reassigning work.
As resource histogram shows utilization and assignment of resources to various activities and their available bandwidth.
ujjal_show
Super Member
Super Member
Posts: 1024
Joined: Thu Sep 17, 2015 12:59 pm

Re: Oliver 175 - 59th Question

Sun Nov 01, 2015 5:13 pm

Uploaded the pic, and The project can probably not be finished as scheduled because of over allocation of resource.
need to be resource leveling.
avtarjs
Posts: 5
Joined: Mon Dec 21, 2015 9:33 am

Re: Oliver 175 - 59th Question

Sun Jan 03, 2016 5:36 pm

Screen Shot 01-03-16 at 11.05 PM.PNG
Screen Shot 01-03-16 at 11.05 PM.PNG (49.04 KiB) Viewed 7735 times
ujjal_show
Super Member
Super Member
Posts: 1024
Joined: Thu Sep 17, 2015 12:59 pm

Re: Oliver 175 - 59th Question

Sun Jan 03, 2016 5:48 pm

hey.. do you need more discussion? answer already explained in above.
vsram
Posts: 3
Joined: Thu Jun 23, 2016 4:18 am

Re: Oliver 175 - 59th Question

Mon Jun 27, 2016 6:26 am

That does not seem to be correct option. The right answer is option-1 as you can see overloaded vs available hours which is "Overloaded (more than 10points) Vs Available (little more than 7points) as per the diagram chart. 1 Point is 25% on the vertical scale. Since the remaining work after full allocation is 10-7 = 3 (approx.) which cannot be allocated, the project will be delayed. Hence the option " The project can probably not be finished as scheduled" seems to be the correct answer......Please correct me if i am wrong..experts!
sarawat
Contributor
Contributor
Posts: 181
Joined: Wed Jul 08, 2015 9:24 am

Re: Oliver 175 - 59th Question

Wed Jun 29, 2016 12:27 pm

option 1 seems to be correct.

you may refer page 265 of PMBoK [ the paragraph that talks about resource calendars ]

Thanks n Regards,
Sanjay Singh Rawat