Project Scope as an input to QC

Exclusive forum for iZenBirdge PMP® clients
bs_pani
Super Member
Super Member
Posts: 663
Joined: Mon Sep 22, 2014 3:36 pm

Project Scope as an input to QC

Mon Oct 20, 2014 2:32 am

Why is project scope is not an input to Qualify Control process?

I know Scope baseline is input to Plan Quality management and the output of Plan Quality management is Quality Management plan which is subsidiary plan for Project management plan. And Project management plan is is an input to Quality Control. But scope is not a direct input to QC.

But is not it Scope should be a direct input to the Quality Control? How we are going to vet the deliverable if we don't have the scope with us?

Cheers,
Bha ba ni :)
User avatar
saket
Site Admin
Site Admin
Posts: 3120
Joined: Sat Dec 07, 2013 10:37 pm

Re: Project Scope as an input to QC

Tue Oct 21, 2014 5:14 am

Project Management Plan includes scope baselines ( Project Scope Statement and WBS ), so it is included.
Attachments
ControlQuality.png
ControlQuality.png (66.08 KiB) Viewed 2647 times
Explore our online PMP Program , it makes PMP Easy :-) http://goo.gl/ZmD3xF

Image Image Image Image
bs_pani
Super Member
Super Member
Posts: 663
Joined: Mon Sep 22, 2014 3:36 pm

Re: Project Scope as an input to QC

Tue Oct 21, 2014 3:55 pm

Dear Saket,

Ah!!! :roll: now I could say we need WBS and WBS dictionary more than Scope Statement for vetting the deliverable.

Btw Project Management Plan is input to almost all the Process, then why do we need individual item as an input? :(

For many process PMBOK talk about the item that is taken as an input for any specifics process from the Project Management Plan. But for Quality Control it does not specifically stating item like Scope Statement, WBS and WBS dictionary from the Project Management Plan is an input to the Quality Control.

Cheers,
Bha ba ni :)
User avatar
saket
Site Admin
Site Admin
Posts: 3120
Joined: Sat Dec 07, 2013 10:37 pm

Re: Project Scope as an input to QC

Wed Oct 22, 2014 12:57 am

Yes you do see such level of discrepancy in PMBOK, sometime they our explicit focus on one item of Project management plan by showing it as separate input, Just take a learning of it... and you can give feedback to PMI, they will fix some ine PMBOK ver 6 :-)
Explore our online PMP Program , it makes PMP Easy :-) http://goo.gl/ZmD3xF