PMP question

Discuss PMP doubts, tips and lesson learned. iZenBridge makes PMP® Certification easy
kashifmohd2000
Posts: 1
Joined: Fri Oct 26, 2018 9:17 am

PMP question

Sun Jul 21, 2019 11:08 am

You have just been authorized to manage a new project for your company. Which of the following best describes your first action ?
A. Create WBS
B. Develop Project Charter
C. Develop Project Management Plan
D. Figure out who has a stake in the project

Source answer given is C ,
but my answer is D , any explanation please.
prosanta
Posts: 5
Joined: Mon Oct 29, 2018 5:00 am

Re: PMP question

Fri Dec 13, 2019 4:06 pm

It should be D
manishpn
Expert
Expert
Posts: 2862
Joined: Sat Jan 04, 2014 3:55 pm

Re: PMP question

Tue Jan 21, 2020 5:46 pm

kashifmohd2000 wrote:You have just been authorized to manage a new project for your company. Which of the following best describes your first action ?
A. Create WBS
B. Develop Project Charter
C. Develop Project Management Plan
D. Figure out who has a stake in the project

Source answer given is C ,
but my answer is D , any explanation please.
The questions mentions that you as PM are authorized, this implies that PC is already developed
From the remaining options provided, D is next best options, as developing PMP will need identification of right stakeholders for their inputs to plan
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
binesh007
Posts: 5
Joined: Wed Feb 05, 2020 5:37 am

Re: PMP question

Wed Feb 05, 2020 8:00 am

Business case and agreements (output from conduct procurement process) are inputs for the first iteration of stakeholder identification before Develop project charter. So here some stakeholders are already identified and documented. So option C makes sense to choose.
manishpn
Expert
Expert
Posts: 2862
Joined: Sat Jan 04, 2014 3:55 pm

Re: PMP question

Wed Feb 05, 2020 9:25 pm

binesh007 wrote:Business case and agreements (output from conduct procurement process) are inputs for the first iteration of stakeholder identification before Develop project charter. So here some stakeholders are already identified and documented. So option C makes sense to choose.
The stakeholders list mention in PC is not exhaustive, developing PMP needs a wider engagement beyond what is mentioned in the PC.
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist
http://www.izenbridge.com/blog/7-effect ... ification/
Viswanathan Raju
Posts: 11
Joined: Sat Nov 02, 2019 6:17 am

Re: PMP question

Fri May 29, 2020 11:33 am

Since PC is the input for PMP and already the key stakeholder list is available on PC,the PM shall start PMP which will be reviewed and updated iteratively.