Contingency Reserves

Thu Jun 25, 2020 1:35 pm

1. Can we utilize the contingency reserves left for an activity for another activity?
2. What is the procedure for using unutilized contingency reserve for an activity to another activity?
manishpn
Expert
Expert
Posts: 2862
Joined: Sat Jan 04, 2014 3:55 pm

Re: Contingency Reserves

Thu Jul 02, 2020 7:51 pm

We discussed in clarification session as well

sumitgoyal27 wrote:
Thu Jun 25, 2020 1:35 pm
1. Can we utilize the contingency reserves left for an activity for another activity?
Yes, through a CR , if the change is withing approval limits of PM then it need not go to CCB

2. What is the procedure for using unutilized contingency reserve for an activity to another activity?
Again, through CR,
Br,
Manish P
PMP, PMI - ACP, SAFe Agilist