September 5th 2020 , PMP Clarification @ 7:00 PM IST

One spot to pull in the announcement of exclusive webinar and to post further doubts and queries
srishti
Posts: 17
Joined: Tue Feb 04, 2020 6:39 am

September 5th 2020 , PMP Clarification @ 7:00 PM IST

Wed Aug 26, 2020 12:41 pm

Use this thread to post your queries, we will discuss in the Webinar.

Day/Date:- Sat/September 5th, 2020

Time:- 7:00 - 8:00 PM IST + 5:30 GMT

This session will be taken by Manish Panchmatia


Get Registered: https://us02web.zoom.us/meeting/registe ... SVcXVhN4vg

Regards
Srishti
ks
ksabhi01@yahoo.com

Re: September 5th 2020 , PMP Clarification @ 7:00 PM IST

Sat Sep 05, 2020 4:44 am

Lara, Programmer, was supposed to work on the user story 1, which, is estimated to be at 5 ideal days. Due to some illness, Lara had to take sudden leaves. User Story 1 was newly assigned to Maria, who was working as Senior Programmer. What effect will be on the ideal days estimation of the user story?
a. Since Maria is Senior Programmer as compared to Lara so the ideal days estimation will be decreased.
b. Since User Story 1 was suddenly assigned to Maria so the ideal days estimation will be increased.
c. Ideal days estimation will remain the same.
d. Cannot tell about ideal days estimation with the given information.
Answer and detailed explanation :
sumitgoyal27
Participant
Participant
Posts: 63
Joined: Wed Jun 24, 2020 2:31 pm

Cost benefit analysis

Sat Sep 05, 2020 10:05 am

During the design process for a mining plant, the project team conducted a cost-benefit analysis based on current commodity prices. However, during the project work, commodity prices fluctuate tremendously. This risk was identified, but the team did not expect such major fluctuations. Now the project may be unviable. What should the project manager do?
A. Immediately escalate the issue to management and the stakeholders.
B. Work with the project team on a solution to make the project viable.
C. Issue a change request to cover the increased costs.
D. Perform a financial analysis based on the updated information.

The correct answer is A however I marked D. Can you please explain??
Source is PMI Mock test.
sumitgoyal27
Participant
Participant
Posts: 63
Joined: Wed Jun 24, 2020 2:31 pm

Risk report and risk register

Sat Sep 05, 2020 10:08 am

A project manager is preparing the monthly project status report. Some new risks have been identified that could impact important key milestones.
A. Risk report and risk register
B. Organizational process assets and risk register
C. Risk report and risk management plan.
D. Risk report and lessons learned repository.

Can you please explain why risk report is required for the status report?
sumitgoyal27
Participant
Participant
Posts: 63
Joined: Wed Jun 24, 2020 2:31 pm

Re: September 5th 2020 , PMP Clarification @ 7:00 PM IST

Sat Sep 05, 2020 10:17 am

A project manager is reviewing approved change requests made within the past month. The process has been efficient but the implementation is taking longer than originally planned.
What should the project manager do?
A. Return the change requests to the change control board (CCB) for further review.
B. Ask stakeholders to raise only critical changes.
C. Request additional resources.
D. Follow change management procedures to monitor implementation.

The correct answer is D. I have a doubt in this question regarding change management procedures because IMO implementation is not covered under change management rules. Can you please explain?
sumitgoyal27
Participant
Participant
Posts: 63
Joined: Wed Jun 24, 2020 2:31 pm

Re: September 5th 2020 , PMP Clarification @ 7:00 PM IST

Sat Sep 05, 2020 10:26 am

A project needs resource support from a supplier because several team members have been transferred to another project. Concerns arise about the cost risk of using a supplier at this stage of the project. The project manager is working with the procurement team to establish specifications and the type of contract that should be used. What type of contract should the project manager recommend?

A. Cost-plus incentive fee (CPIF)
B. Firm fixed price (FFP)
C. Fixed-price incentive fee (FPIF)
D. Time and Material (TM)

Can you please explain this?? The correct answer is C but I was not able to understand the logic.
sumitgoyal27
Participant
Participant
Posts: 63
Joined: Wed Jun 24, 2020 2:31 pm

Re: September 5th 2020 , PMP Clarification @ 7:00 PM IST

Sat Sep 05, 2020 10:31 am

A stakeholder believes that information is lacking and asks the project manager about the project's status. What should the project manager do?
A. Ask the stakeholder if they are checking their mail.
B. Check the communications management plan to ensure that the stakeholder is included.
C. Send a project status update to all stakeholder
D. Refer to the communications management plan to ensure that all stakeholders are included.

The Correct answer is D however I marked B. Can you please explain??
sumitgoyal27
Participant
Participant
Posts: 63
Joined: Wed Jun 24, 2020 2:31 pm

Re: September 5th 2020 , PMP Clarification @ 7:00 PM IST

Sat Sep 05, 2020 10:35 am

A senior manager wants to use an essential project resource for another project. What should the project manager do?

A. Inform the team and reassign that resource's responsibilities to other team members.
B. Ask the senior manager to provide a replacement.
C. Escalate the issue to the program manager for resolutions.
D. Explain to the senior manager that this resource is fully committed to the project and is unavailable.

The correct answer is C. However, I marked D can you please explain??
sumitgoyal27
Participant
Participant
Posts: 63
Joined: Wed Jun 24, 2020 2:31 pm

Re: September 5th 2020 , PMP Clarification @ 7:00 PM IST

Sat Sep 05, 2020 12:20 pm

During project execution, a stakeholder requests a change to ensure that the final product will satisfy their requirements. What should the project manager do next?
A. Reject the request and record it in the product backlog.
B. Approve the request only if it will not have an impact on the budget or schedule.
C. Submit a change request, as per the project's change control process.
D. Ask the team to determine the impact of the request on budget and schedule.

This is a PMI mock question.

I choose D as the answer but it was incorrect and the explanation given is mentioned below:-
Verifying that the changes are registered, assessed, approved, and tracked and communicating final results to stakeholders is the responsibility of the project manager.
sumitgoyal27
Participant
Participant
Posts: 63
Joined: Wed Jun 24, 2020 2:31 pm

Re: September 5th 2020 , PMP Clarification @ 7:00 PM IST

Sat Sep 05, 2020 12:29 pm

Can you please explain on configuration management plan??
As per my understanding configuration management plan handles the revisions in project documents so that everyone works on the same revision number.
sumitgoyal27
Participant
Participant
Posts: 63
Joined: Wed Jun 24, 2020 2:31 pm

Re: September 5th 2020 , PMP Clarification @ 7:00 PM IST

Sat Sep 05, 2020 12:31 pm

In the work breakdown structure, what is the first level of decomposition? Is it the project name or decomposition below the project name?
sumitgoyal27
Participant
Participant
Posts: 63
Joined: Wed Jun 24, 2020 2:31 pm

Re: September 5th 2020 , PMP Clarification @ 7:00 PM IST

Sat Sep 05, 2020 12:56 pm

Can you please tell briefly about the sequence of activities in the closing process group especially about administrative closure?
sumitgoyal27
Participant
Participant
Posts: 63
Joined: Wed Jun 24, 2020 2:31 pm

Re: September 5th 2020 , PMP Clarification @ 7:00 PM IST

Sat Sep 05, 2020 12:56 pm

Under project schedule network diagram, we have two types of diagrams "Logic bar chart and time-scaled logic diagram". Can you please throw some light on them.
sumitgoyal27
Participant
Participant
Posts: 63
Joined: Wed Jun 24, 2020 2:31 pm

Re: September 5th 2020 , PMP Clarification @ 7:00 PM IST

Sat Sep 05, 2020 1:24 pm

A project to migrate an organization's email system to another platform creates an unexpected, but significant, issue on another business-critical system. What should the project manager do?
A. Revise the project management plan to include the issue.
B. Update the issue log.
C. Inform the stakeholder of the issue.
D. Ask the project team to resolve the issue.

The correct answer is C but I marked B. IMO first, we should update the issue log and then inform the stakeholder based on the criticality of the situation. Please reply.
indrani_deka
Posts: 8
Joined: Tue Aug 04, 2020 10:18 am

Re: September 5th 2020 , PMP Clarification @ 7:00 PM IST

Mon Sep 07, 2020 11:24 am

Here is the link of PMP Clarification session for 5th Sep 2020
https://vimeo.com/455454241/9acf35cb89